Memorial Stadium Construction UpdateMemorial Stadium Construction Update

Memorial Stadium Construction Update

Lincoln - Construction workers are scheduled to begin installation of steel columns for the Tom and Nancy Osborne Athletic Complex on Monday, Feb. 14. 

 

The installation will begin on the East side of North Stadium.  Some of the columns are more than 75 feet in height as they will span the entire seven stories of the new complex.  Davis Erection has moved the crane into position for this next step of construction.  The position of the crane will eliminate running on the Ed Weir Outdoor Track until mid-March.